Mari kita memerah otak dalam matematik pulak untuk kira kos bahan mentah.
Ikutkan sebelum sesuatu projek di buat, kita kena buat kira-kira untuk budget atau anggaran kos. Tapi reban dah siap baru nak kira kos, larilah budget. So untuk kes study, aku ambil la reban 2 tingkat 10 sel ni.
Bahan-bahan yang diperlukan,
BRC 1/2in G18 - RM5 per 3kps (12in x 36 in)
a. Lebar tapak - 2 kaki @ 24in
b. Panjang - 7.5 kaki @ 90in
c. Tinggi L1 - 20in (i) dan 10in (ii)
d. Tinggi L2 - 14in
e. Jumlah dinding L1 & L2 - 6 keping setiap level.
Maka luas BRC yang diperlukan;
= tapak + dinding L1 + dinding L2 + subdinding L1 + subdinding L2
= [ (a x b) x 2 level ] + [(b x ci) + (b x cii)] + [(b x d x 2)] + [(ci + cii)/2 x a x 6] + [d x a x 6]
= [(24 x 90) x 2] + [(90 x 20) + (90 x 10)] + [(90 x 14 x 2)] + [(20 + 10)/2 x 24 x 6] +[14 x 24 x 6]
= 4,320 + [1,800 + 900] + 2,520 + 2,160 + 2,016
= 13,716 inci persegi
= 13,716 / 144 kaki persegi
= 95.25 kps
Tambahan 10% untuk lipatan = 95.25kps x 1.1% = 104.775 kps
Harga untuk BRC sahaja 104.775 kps x RM5 / 3kps =
RM174.62
PVC 1/2in - RM0.375 per 12inci & Connector
Tinggi kaki LG - 16in x 6 batang x RM0.375 / 12 = RM3.000
Tapak lebar LG - 22in x 3 batang x RM0.375 / 12 = RM2.625
Connector LG - Elbow x 6 x RM0.40 = RM2.40
Total = RM8.025
Tinggi kaki L1 - 19in x 6 batang x RM0.375 / 12 = RM3.5625
Tapak panjang L1 - 90in x 2 batang x RM0.375 / 12 = RM5.625
Tapak lebar L1 - 24in x sebatang x RM0.375 / 12 = RM0.75
Connector L1 - T x 6 x RM 0.60 = RM3.60
Total = RM13.60
Tapak panjang L2 - 90in x 2 batang x RM0.375 / 12 = RM5.625
Connector L2 - Elbow x 4 x RM0.40 + T x 2 x RM0.60 = RM2.80
Total = RM8.425
Water Feeder - 96in x 2 batang x RM0.375 / 12 = RM6.00
Connector - Elbow x 2 x RM0.40 + Cap x 2 x RM0.30 = RM1.40
Bridge - 30in x sebatang = RM0.9375
Total = RM8.3375
Grand Total = 8.025+13.6+8.425+8.3375 = RM 38.39
(PVC = 73.5kaki @ RM27,56, Elbow x 12 unit @ RM4.80, T x 8 unit @ RM4.80 dan Cap x 2 unit @ RM0.60)
Bumbung, RM2.75 per 2.5kps (12in x 30in)
32in x 30in x 6keping = 5,760in psq
= 5,760 / 144 kps
= 40kps
Harga = 40kps x RM2.75 /2.5kps =
RM44.00
Others
Nipple x 10 x RM3.5 = RM35.00
1/2" kayu 90in x 2 x RM1.20 / 72in = RM3.00
Cable tie x 100pcs = RM5.00
PPE Tape = RM0.50
Lock Wire, Gun Tacker
Total = 35.00 + 3.00 + 5.00 + 0.50 =
RM43.50
Maka JUMLAH KOS BAHAN;
= RM174.62 + RM 38.39 +RM44.00 + RM43.50
= RM 300.51
Mark-up dari kos bahan adalah 1/3 iaitu 35% = RM 300.51 x 135% =
RM405.6885
Upah tenaga kerja mahir RM100 x 2 hari =
RM200.
Harga reban 2 tingkat 10 sel ini = RM 405.6885 + RM 200 =
RM 605.6887
Maka harga reban ini boleh lah digenapkan menjadi
RM 600.00
Disebabkan harga reban yang mahal, aku bercadang untuk meng-cost-down-kan sedikit reban yang akan datang. Mungkin menggunakan BRC dari 1/2in x 1/2in ke 1/2in x 1in dan mempelbagaikan material BRC di bahagian dinding atas.